project description
Redstone Scope of Services: Full Architectural Services
Size: 54,000 s.f.
Estimated Completion: May, 2022
Location: Genesee County, MI
Original Project Budget: $20,000,000
Final Construction Cost: $22,593,000
Original Completion Date: September 2022
Completion Date: August 2024
Client Contact:
Rhona R. Ihm, Family Division Administrator
Genesee County
7th Circuit Court
(810) 768-7088
Contractor: E & L Construction Group
Number of Staff: 50
Redstone Personnel: Dan Redstone, FAIA, Principal
Detention Consultant: Elevatus Architecture
The new juvenile detention facility was designed upon an Evidence Based Model and includes day treatment and detention components. The facility consists of classroom and therapy spaces, full- service prep kitchen/cafeteria, gymnasium and exterior recreation space, shared administration and clerical area, Central Security Control and three separate housing pods. Each pod includes a classroom, day room, meeting and office spaces, along with 16 beds.
The new facility is located adjacent to the existing GVRC to the west on Pasadena Avenue and was completed in the spring of 2024.